Project Background ![]()
RIC has close to 3 thousand projects to monitor every year with a budget
of $1 billion dollars.
Scope of Services ![]()
Javelin developed and implemented a project control database and a
P3 scheduling system including resources and earned value progress
update processes. Total Project Control System, Resource balancing,
EV design and reporting 'On site' service.
![]()
Ejigbo
Water Supply SchemeProject Background
$83.5 million project for the construction of 162 km long water pipeline, treatment
plants, booster stations and 8,000m3 storage tanks capacity.
Javelins Role ![]()
Designed and implemented project control system for measuring, monitoring and
controlling project performance.
Evaluation of organisation's technical, managerial and financial capabilities.
Design of organizational and business processes for capital program planning and management; project planning; and professional project management and control.
![]()
Ile-Ife
Township Water Distribution Network.Project Background
$70 million project to construct a new water supply
and distribution network to serve a population of
600,000 people.
Javelins Role ![]()
Prepared construction programmes and detailed work plans for tender submission.
Prepared resource schedules and estimates.
Prepared budget statements and cash flow analysis.
Designed and implemented project control system for measuring, monitoring and controlling project performance.
![]()
M5
East FreewayProject Background
The M5 East major Sydney freeway including the longest Australian road tunnel.
The total value of the job was more than $650 million dollars. The project
was completed three months ahead of time and ahead of budget.
Javelins Role ![]()
Javelin played a major part in winning the tender for the largest single awarded
construction project in Australia. We provided Construction programs, Project
progress control and Reporting service.
![]()
Lihir
Island Gold MineProject Background ![]()
Gold mine project on Lihir Island Pacific Ocean,
Solomon Islands with a $50 million budget.
Javelins Role ![]()
On this project we covered everything. Tender, Procurement, Construction Programs
through completion and change contract process. Total Project Control System
Tender and Construction
Programs, Project Progress control and reporting, claims and ‘On site’ and ‘Online’ planning
service.
![]()
Malacca
Straight Gas PipelineProject Background
6.5 kilometers of gas pipeline across Malacca Straight. This $20 million project
was the most challenging undertaken by Javelin. The technical complexity
and new technology made this project very difficult for contractors and sub-contractors.
Javelins Role ![]()
Total Project Control System, Construction Programs, Project Progress control
and reporting, ‘Online’ planning service.
![]()
Project Background ![]()
Melbourne City Link Project major toll way. The total value of the job was
more than $2 billion dollars.
Javelins Role ![]()
Javelin designed and implemented a time and KPI progress monitoring system
for the $500 million Western Link part of the project. The project was completed
on time. The planning/scheduling software used was Primavera P3, SureTrak,
MS-Access databases, Excel spreadsheets and graphical reports.
![]()